Skip to main content

Buying guide

Changeover Switch and ATS for a Generator: Types, Sizing, Neutral and Safe Connection

Updated 12 min readBy the EU Enterprise technical team

Any generator that feeds a building’s wiring needs a changeover switch or an automatic transfer switch (ATS), so the load is connected to the mains or to the generator but never to both. Size it for the larger of the generator’s full-load current and the main breaker rating, and let a qualified electrician choose the poles to suit the earthing system. A manual switch suits a set you start by hand; an ATS starts the set and transfers the load by itself.

The short answer

  • A transfer device is essential. A generator feeding a building’s wiring needs a changeover switch or ATS, so the load is never on both sources.
  • Manual or automatic. A manual I-0-II switch suits a hand-started set; an ATS detects a mains failure, starts the set, transfers the load and switches back.
  • Size by current. Take the larger of the generator’s full-load current and the main breaker rating, then round up.
  • Poles follow the earthing. Switching the neutral depends on the earthing system and the generator neutral; the electrician decides under the local code.

Why a transfer device is essential

Without a transfer device, a generator on the building wiring can push power back into the supply cable (backfeed). The local transformer works in both directions and steps the voltage up to thousands of volts, so a line worker who believes the line is dead can be killed.

If the mains returns while the generator is connected, the supplies meet out of step: the generator can be badly damaged and the wiring can catch fire.

Manual changeover switch or ATS

Manual changeover switches

A manual changeover switch has three positions: I (mains), 0 (off) and II (generator). It is break-before-make, so the two sources can never be joined. The 0 position isolates the load from both and, on many models, can be padlocked; a pause there lets running motors slow down. Avoid switches with exposed live parts.

Automatic transfer switches (ATS)

Transfer devices compared
TypeHow it worksWatch out for
Manual changeover switchHand-operated, I-0-II, break-before-makeNeeds someone on site
Dedicated ATSSwitch, motor and controller in one product (IEC 60947-6-1)Settings must suit your supply
Motorised changeover switchSwitch driven by a motor operator from a separate controllerParts must be matched
Interlocked contactor pairTwo contactors, mechanically and electrically interlockedCoils chatter on low voltage; not an isolator
Interlocked motorised breakersTwo MCCBs or ACBs, one closed at a time, with built-in protectionUse the maker’s interlock kit

In a contactor pair, each coil is fed through the other’s normally closed auxiliary contact, with the maker’s mechanical interlock. Size each contactor by its AC-3 current when motors are connected, AC-1 only for purely resistive loads (see our contactor sizing guide), and add a lockable switch-disconnector for isolation.

What the ATS controller does

  1. Detects mains failure: it compares the voltage on every phase, often frequency too, with set limits.
  2. Starts the generator: after a few seconds (often 1–3 s) to ride through brief dips, it switches a volt-free start contact.
  3. Transfers: once generator voltage and frequency are within limits, it opens the mains side, pauses at off and closes the generator side.
  4. Retransfers: it switches back once the mains has stayed healthy for a set time, often a few minutes.
  5. Cools down: the set runs unloaded for a few minutes, as its maker advises, then stops.

With large motor loads, a longer pause at off (delayed transition) lets the motors’ residual voltage decay. Some small units have no start output and transfer once a hand-started set comes up. An AMF (auto mains failure) panel combines generator control and transfer.

How to size a changeover switch

The switch carries mains current in position I and generator current in position II, so it must be rated for the larger, and at least as high as the breakers or fuses that protect it.

  • Single-phase: I = S ÷ V (S in VA, V = 230 V).
  • Three-phase: I = S ÷ (√3 × V) (V = 400 V between lines).

Use the highest kVA on the nameplate (the standby rating, if given); for any set rated only in kW, divide by the nameplate power factor (usually 0.8 for diesel sets). Round up to the next standard rating. Ratings apply at a stated ambient, often 40 °C, so check the derating for a hot panel.

Generator full-load current
GeneratorSupplyFull-load current
5 kVASingle-phase, 230 V21.7 A
7.5 kVASingle-phase, 230 V32.6 A
100 kVAThree-phase, 400 V144.3 A
250 kVAThree-phase, 400 V360.8 A

Worked example: home or shop generator

  1. 7.5 kVA single-phase set: I = 7,500 ÷ 230 = 32.6 A. Main breaker (assumed): 40 A.
  2. The larger is 40 A: choose at least 40 A, or 63 A for headroom in a hot enclosure.
  3. The switch does not limit the load: on generator, keep it under 32.6 A or feed only an essential-loads board.

Worked example: factory set

  1. 250 kVA, 400 V three-phase set: I = 250,000 ÷ (√3 × 400) ≈ 361 A.
  2. Main incomer MCCB (assumed): 400 A, so choose a device with an AC-33 rating of 400 A at 400 V.
  3. With a 630 A incomer, transfer the whole site at 630 A and shed load on generator, or feed essential loads through a 400 A switch to a sub-board.

Poles and the neutral

This is the electrician’s decision, under the local code and the utility’s rules. Two rules are fixed: the generator neutral is earthed in one place only, and a combined neutral and earth (PEN) conductor is never switched or broken.

Common neutral arrangements
ArrangementPolesGenerator neutralWhere it fits
Switched neutral2-pole (single-phase), 4-pole (three-phase)Earthed on the generator sideTT systems; incomers with earth-leakage protection
Solid neutral1-pole plus neutral link, 3-poleEarthed only via the main neutral-earth linkOnly where the local code and the utility expressly allow it; many codes require the generator’s earthing not to depend on the supply
PEN conductor (TN-C)Never switched–Breaking it can make metalwork live

With two neutral-earth links, neutral current flows in earth conductors and metalwork, and RCCBs can trip without a fault. With none (a floating generator neutral), earth faults can go undetected. Some generators have an internal neutral-earth link: check the manual or test it. In a TT system, where the earth comes from the building’s own electrode rather than the supply, the neutral counts as live and is normally switched.

Ratings to check on the datasheet

Utilisation category

IEC 60947-6-1 (transfer switching equipment) rates duty as AC-31 for non-inductive or slightly inductive loads and AC-33 for motor loads or mixed loads including motors; suffix A means frequent operation and B infrequent, as in AC-33B. Switches to IEC 60947-3 use AC-21 (resistive), AC-22 (mixed resistive and inductive) and AC-23 (motors); AC-20 is off-load only. With motors connected, the AC-33 or AC-23 current must cover the load.

Short-circuit rating

The switch must withstand the prospective fault current where it sits, usually highest on the mains side near a large transformer. Class PC (switch-based) devices make and withstand a fault but rely on an upstream fuse or breaker to clear it: check the short-time withstand current (Icw), making capacity (Icm) or conditional rating with a named fuse or breaker. Class CB (breaker-based) devices clear it themselves; see our MCB vs MCCB vs RCCB guide.

Enclosure and IP rating

Many switches and ATS units have an IP20 front and must sit in an enclosure: IP4X or better indoors, IP54 or higher outdoors or in dusty rooms (5 = dust-protected, 4 = splashing water). Keep it out of direct sun and label it: I = mains, II = generator.

Generator, UPS and solar inverter together

  • UPS or battery inverter: it has its own input and output and is not a changeover switch. Feed its input from the changeover output; its output feeds only its own circuits and must never be joined in parallel with the mains or generator supply to those circuits. Any bypass switch you add must be break-before-make, unless the UPS maker supplies and specifies a make-before-break maintenance bypass. Size the generator for the loads plus the charger.
  • Grid-tie solar inverter: it is designed to stop when the mains fails, but a running generator looks like mains to it. On the load side of the changeover it can run on the generator, and when solar output exceeds the load, power flows back into the generator, which can trip or be damaged. Check before connecting. Common answers are an inverter connection on the mains side of the changeover, so it stays off on generator, or a controller made for solar with generators.
  • Hybrid inverter: use its generator input or settings so it cannot export into the generator; see our solar accessories.

Checklist before you buy and install

  1. Agree the earthing system, generator neutral and number of poles with the electrician.
  2. Work out the generator current, compare it with the main breaker and round up.
  3. Choose manual or ATS; check sensing, delays, start signal and testing.
  4. Check the utilisation category (AC-33 or AC-23) and the short-circuit rating.
  5. Choose the enclosure and IP rating, a lockable off position and clear labels.
  6. Size the cables and the generator output breaker (see our cable sizing guide).
  7. Check the UPS and solar connections.
  8. On three-phase, match the generator’s phase rotation to the mains; test transfer and retransfer on load.

Browse our switches and distribution panels, plus circuit breakers, contactors & motor starters and cables (brands on the site include ABB, Schneider Electric and Chint). Send us the generator nameplate, your main breaker rating and a photo of the board on WhatsApp and our team will help you choose.

Frequently Asked Questions

What size changeover switch do I need for my generator?

Work out the generator’s full-load current: kVA × 1,000 ÷ 230 for single-phase, or kVA × 1,000 ÷ (1.732 × 400) for three-phase. Compare it with the main breaker on the mains side, take the larger figure and round up to the next standard rating. For example, a 7.5 kVA single-phase set draws 32.6 A, so with a 40 A main breaker choose at least 40 A, or 63 A for headroom in a hot enclosure. A 250 kVA three-phase set draws about 361 A, so choose 400 A if the main breaker is 400 A or less.

What is the difference between a changeover switch and an ATS?

A changeover switch is operated by hand: when the mains fails, you start the generator and turn the switch from I (mains) through 0 (off) to II (generator). An automatic transfer switch does this by itself. Its controller detects the mains failure, starts the generator, transfers the load once the generator is stable, and switches back after the mains has stayed healthy for a set time. Both must be break-before-make, so the two supplies can never be connected together.

Should a changeover switch switch the neutral?

It depends on the earthing system and on how the generator neutral is earthed, so a qualified electrician should decide under the local code and the utility’s rules. In a TT system the neutral is treated as a live conductor and is normally switched, with a 2-pole or 4-pole switch and the generator neutral earthed on its own side. A combined neutral and earth (PEN) conductor must never be switched. Whatever the arrangement, the generator neutral must be earthed in one place only.

Can I connect a generator to my house without a changeover switch?

No. Feeding the house wiring from a generator without a changeover switch or ATS risks backfeed, which can electrocute line workers, and serious damage when the mains returns. Never use a plug-to-plug lead into a socket. Without a transfer device, the only safe use is to plug appliances directly into the generator’s own sockets with suitably rated leads, with the generator running outdoors, well away from doors, windows and vents, because its exhaust contains deadly carbon monoxide. A permanent connection needs a transfer device installed by a qualified electrician.

Can I use a changeover switch with a solar inverter or UPS?

Yes, with care. A UPS or battery inverter is fed from the changeover output and supplies only its own circuits; its output must never be joined in parallel with the mains or generator supply to those circuits. A grid-tie solar inverter on the load side of the changeover can run on the generator and push power back into it when solar output exceeds the load. Ask the installer to connect it on the mains side of the changeover, or to fit a controller made for solar with generators.

Why does my ATS keep switching between mains and generator?

This is called hunting. Common causes are a weak mains supply whose voltage drops below the dropout setting as soon as the load is transferred back, voltage limits set too close together, a retransfer delay that is too short, an overloaded generator whose voltage or frequency sags, or a loose sensing or neutral connection. Have an electrician measure both sources under load, widen the gap between the pickup and dropout settings, lengthen the retransfer delay and check the generator size.

Related guides